Olkaria I Geothermal Power Station: KenGen Injects 63.3MW into National Grid After Upgrade

Home » Energy » Geothermal » Olkaria I Geothermal Power Station: KenGen Injects 63.3MW into National Grid After Upgrade

Project Factsheet

LocationOlkaria Geothermal Field, Hell’s Gate National Park, Naivasha (Nakuru County), Kenya

Capacity Increase45 MW to 63.3 MW (+18.3 MW net gain across Units 1, 2, and 3)

Estimated CostKSh 15.6 billion

Scope of WorksReplacement of aging steam turbines and generators, installation of a new gas extraction system, rehabilitation of the steam-gathering pipework, and construction of a new gas-insulated substation

Operational LifespanExtended by 25+ years using the existing steam resource

TimelineConstruction began in August 2023, with unit grid synchronization and commissioning rolling out in 2026

Project Team and Key Partners

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *