Inside Ørsted’s Progress on the Revolution Offshore Wind Project off Rhode Island

Home » Energy » Wind power » Inside Ørsted’s Progress on the Revolution Offshore Wind Project off Rhode Island

Revolution Wind Project Factsheet

Project Overview

  • Name: Revolution Wind
  • Type: Offshore wind farm (first multi-state project in the U.S.)
  • Capacity: 704 MW
    • 400 MW to Rhode Island
    • 304 MW to Connecticut
    • Powering over 350,000 homes
  • Emissions Offset: Avoids over 1 million metric tons of CO₂ annually—equivalent to removing about 150,000 cars from the road

Location

  • Federal Waters: Approximately 15 miles south of the Rhode Island coast. 32 miles southeast of Connecticut. 12 miles southwest of Martha’s Vineyard
  • Lease Area: BOEM’s OCS-A 0486; separated from a larger lease area in 2020

Development Partners

  • Developers: Ørsted and Global Infrastructure Partners (Skyborn Renewables)
  • History: Initially partnered with Eversource, which exited ownership in 2024

Technology & Infrastructure

  • Turbines: 65 Siemens Gamesa 11 MW (11.0-200 DD)
  • Transmission: Subsea cables to Quonset Business Park (Rhode Island), then underground to the Davisville substation and into the regional grid

Timeline & Permitting

  • Environmental Review: Draft EIS released in August 2022. Final EIS and Joint Record of Decision signed in August 2023 by BOEM, NMFS, and USACE
  • Construction: Began in 2023
  • First Turbine Installed: September 2024
  • Target Commercial Operation Date (COD): 2026

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *