Outerbridge Crossing Study Finds Widening Could Cost Twice as Much as Replacement

Home » Transport » Bridges » Outerbridge Crossing Study Finds Widening Could Cost Twice as Much as Replacement
Outerbridge Crossing Widening Study Finds Expansion Could Take Nearly Twice as Long as Building a New Bridge

Outerbridge Crossing Rehabilitation and Future Replacement: Project Factsheet

  • Location: Between Staten Island, New York, and Perth Amboy, New Jersey, USA
  • Asset owner/operator: Port Authority of New York and New Jersey
  • Existing crossing: Approximately 1.76 miles long
  • Existing configuration: Four traffic lanes
  • Widening objective: Six lanes and a pedestrian/bicycle shared-use path
  • Engineering consultant: HDR
  • Widening alternatives evaluated: Symmetrical Scheme S2 and Asymmetrical Scheme A2
  • Key structural finding: Approximately 55%–57% of north truss members would require significant strengthening
  • Estimated widening impact: Significant roadway closures and traffic disruption for up to eight years
  • Comparative finding: Widening could cost and take almost twice as much as constructing a new bridge
  • Widened structure’s estimated service life: Approximately 30 years
  • New bridge reference service life: At least 100 years
  • Approved rehabilitation allocation: $336 million
  • Rehabilitation duration: Four years, with the crossing remaining open to traffic
  • Replacement planning: Expected early in the 2036–2045 capital plan period
  • Study document: Outerbridge Crossing Widening Feasibility Study – Scheme Development Package, September 30, 2026

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *