Project fact sheet
Project nameSeagreen Offshore Wind Farm
LocationNorth Sea, approximately 27km off the Angus coast, Scotland
CountryUnited Kingdom
Project typeFixed-bottom offshore wind farm
Status (2026)Fully operational
Installed capacity1.075GW (approximately 1.1GW)
Number of turbines114
First powerAugust 2022
Commercial operationOctober 2023
Annual generationElectricity for more than 1.6 million homes
Carbon reductionMore than 2 million tonnes of CO₂ avoided annually
Operations baseMontrose Port, Scotland
Current focusLong-term operations, maintenance and grid integration
Related developmentSeagreen 1A extension remains in development planning.
Project team
Project ownerSeagreen Wind Energy Ltd.
Lead developerSSE Renewables
OperatorSSE Renewables
Equity partnerTotalEnergies
Equity partnerPTTEP
Development rights authorityCrown Estate Scotland
Consent authorityScottish Government
Marine regulatorMarine Directorate, Scottish Government
Operations baseMontrose Port Authority
Transmission connectionNational Grid Electricity Transmission
Primary construction contractor (development phase)SSE Renewables-led delivery team
Wind turbine supplierSiemens Gamesa Renewable Energy
Foundation supplierSSE-led supply chain consortium
Offshore installation contractorsMultiple specialist marine contractors engaged during construction.