Fact Sheet for Singapore New Hydrogen-Ready Power Plant Generation Tender (2026 RFP)

PromoterEnergy Market Authority

Project typeHydrogen-ready combined cycle gas turbine power plants

CapacityUp to 3 units of 600MW minimum capacity

Total planned capacityOver 1.8GW

FuelNatural gas initially, hydrogen-ready

Ownership modelPrivate sector BOO (Build-Own-Operate)

Commercial operation dates:

  • Unit 1: 2031
  • Units 2 and 3: 2032

Tender launched29 April 2026

Bid deadlines:

  • 24 June 2026
  • 30 September 2026

Development timeline for Singapore power plant tender

2023

  • Singapore formalizes centralized process for new generation capacity.

June 2024

  • Second RFP launched for 2029-2030 hydrogen-ready generation capacity.

January 2025

  • PacificLight awarded 600MW hydrogen-ready unit for 2029 delivery.

29 April 2026

  • Third Singapore RFP launched for one 2031 unit plus up to two 2032 units of hydrogen-ready power plants.

24 June 2026

  • Deadline for 2031 unit bids.

30 September 2026

  • Deadline for 2032 unit bids.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *