Project Fact Sheet
ProjectSouth Yakutian Thermal Power Plant
LocationChulman, Neryungri District, Republic of Sakha (Yakutia), Russia
Project typeCombined-cycle gas-fired thermal power plant
DeveloperGazprom Energoholding
Project customerChulman TPP LLC
First commissioned unit110MW gas turbine
Total planned capacity313MW
Generating configurationTwo 110MW gas turbines and one 93MW steam turbine
Fuel sourceNatural gas from the Power of Siberia pipeline
Construction commencementJune 2024
First unit commissioningNovember 25, 2026
Second-phase target2027
Primary purposeElectricity supply to the Eastern Energy System and the Eastern Railway Polygon
Project statusFirst gas turbine commissioned; further generating units remain part of the phased development
Project Team
Gazprom EnergoholdingProject developer and implementing group.
Chulman TPP LLCProject customer.
TEK MosenergoGeneral contractor responsible for construction and installation works.
GEH EngineeringProject monitoring organisation.
Natsproektstroy GroupParent group of TEK Mosenergo, involved in construction delivery.
System Operator of the Unified Energy SystemResponsible for coordinating the integration of the new generating unit into the regional power system.