Summerfield Battery Project

Project Fact Sheet

NameSummerfield Battery Energy Storage System (BESS).

TypeUtility-scale battery energy storage infrastructure.

LocationNear Mannum, in the Murraylands region of South Australia, approximately 55 kilometers east of Adelaide.

Capacity240 MW.

Energy storage capacity960 MWh.

Storage durationFour hours at rated output.

Battery technologySolBank 3.0 lithium-ion battery energy storage system.

Battery equipmentMore than 200 battery containers; the official project information lists 222 containers.

Construction commencementFebruary 2025.

Construction statusMajor construction completed; commissioning underway as of October 2026.

Expected commercial operationsEarly 2027, according to the latest commissioning report.

Project costNot publicly disclosed in the cited sources; a verified USD construction cost is unavailable.

Original developerCopenhagen Infrastructure Partners (CIP).

Current ownershipIntera Renewables, Palisade Investment Partners’ Australian renewable energy platform.

Electricity offtakerOrigin Energy, under a long-term tolling arrangement.

Primary purposeStore electricity and discharge it during periods of higher demand.

Expected household supply equivalentApproximately 70,000 homes for four hours.

Grid connection infrastructureProject substation and transformers, with associated transmission infrastructure.

Key competing developmentReeves Plains battery, planned at 250 MW/1,000 MWh for its first stage, with a potential expansion to 500 MW/2,000 MWh.

Project Team

Original project developerCopenhagen Infrastructure Partners (CIP)

Current project owner and investment platform Intera Renewables

Infrastructure investor and asset ownerPalisade Investment Partners

Battery engineering, procurement and construction contractore-Storage, a subsidiary of Canadian Solar

Battery technology supplierCanadian Solar’s e-Storage division

Construction management contractorBlue Power Partners

Future asset managerPalisade Integrated Management Services (PIMS)

Electricity offtakerOrigin Energy

Regulatory authorityEssential Services Commission of South Australia (ESCOSA)

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *