The TeraWulf Kentucky data center has moved from groundwork to vertical construction. TeraWulf said this week that the first structural steel is going up at its Justified Data campus in Hawesville, where it is building a $4 billion-plus AI campus for Anthropic. The campus will provide about 401 MW of critical IT capacity, with first capacity due in the second half of 2027.
What the TeraWulf Kentucky data center will deliver
The campus sits on the former Century Aluminum smelter site. TeraWulf bought the site in February for $200 million in cash. It also took a 6.8% minority stake in the development entity. The project will be built in phases. As a result, ready-for-service completions are expected from late 2027 through the second quarter of 2028. Construction has reached a new stage. TeraWulf says most of the structural steel for the first building has been delivered and staged. Substantial deliveries for the second building have also arrived. As a result, the work is shifting from foundations to the steel frames of the data halls. The design also uses closed-loop liquid cooling for the high-density AI chips.
Power is already in place. In August, Kentucky regulators approved an electric service agreement for up to 482 MW. Big Rivers Electric Corporation and Kenergy will serve the site. Because it is a former smelter, the site can reuse electrical infrastructure that once served the smelter’s load.
Who is building it, and how is it financed?
Fluor leads the build. On November 4, TeraWulf signed a definitive engineering, procurement, and construction contract with Fluor. The contract uses a guaranteed maximum price for three data center buildings. It also covers testing and commissioning. It follows a limited notice to proceed issued in March. Fluor has not disclosed the contract value. However, it expects to book the award in the fourth quarter, once pricing is set for the first two buildings.
The tenant anchors the financing. Anthropic signed a 20-year lease on July 6. TeraWulf expects the lease to bring in about $19 billion in contracted revenue over the initial term. The lease also carries two five-year renewal options. In addition, Google has agreed to provide credit support for the project’s debt financing. TeraWulf says this should lower borrowing costs. Meanwhile, the company was reported to be lining up about $3.5 billion of debt.

What happens next?
The next steps are delivery and financing. TeraWulf must finish the debt raise, keep the Fluor schedule on track, and bring in power and electrical equipment on time. The company lists financing terms, construction schedules, power availability, and electrical equipment as the main execution risks. The timeline is tight. The first capacity is due in the second half of 2027, and the full 401 MW is due by early 2028. Watch the steel progress, the financing close, and any further expansion, because TeraWulf has also bought a second Kentucky site for a gigawatt-scale campus. AI companies are also securing their own power. For example, Anthropic has reportedly agreed to a $3.4 billion deal for 1.7 GW of gas-fired generators, although the parties have not confirmed it.
Other projects
Elon Musk has asserted that the Terafab project slated for Austin, Texas will be the largest chip manufacturing factory of its kind. The project is a joint venture between Tesla, SpaceX, and xAI. Musk noted that the facility is the next step towards harnessing the power of the sun and also creating a galactic civilization. The CEO of all three companies announced plans for the Terafab in a livestream session on X.