Only one of six major U.S. regional grid operators had a clearly confirmed large-load tariff filing ahead of the November 16 deadline set by the Federal Energy Regulatory Commission (FERC), as the agency’s effort to reform how data centers and other major electricity users connect to the power grid reached a critical stage.
ISO New England submitted proposed tariff revisions on November 13, outlining new transmission services, operating requirements and cost-recovery provisions for large electricity users. The other five operators—PJM Interconnection, the New York Independent System Operator (NYISO), the Midcontinent Independent System Operator (MISO), the California Independent System Operator (CAISO) and the Southwest Power Pool (SPP)—were at different stages of their response processes, with SPP given until November 20.
The filings follow FERC’s June 18 show-cause orders, which directed the six regional operators to explain why their existing rules adequately address the challenges of connecting large loads or propose changes to their tariffs.
The issue has become increasingly important as data centers, advanced manufacturing facilities and other electricity-intensive developments seek access to transmission capacity. FERC’s review covers how these facilities are studied, what operating conditions they must meet and how the cost of the necessary grid upgrades is recovered.
ISO New England puts its proposal on file
ISO New England’s November 13 filing, listed under docket ER27-484-000, provides the clearest example so far of the tariff changes being developed in response to FERC’s orders.
The proposal introduces three new transmission service arrangements for large loads, alongside revised application and study procedures. It also establishes operating requirements covering load forecasting, telemetry, communications, ramp rates and outage coordination.
One feature is a price-based redispatch mechanism for non-firm transmission service, with a proposed $250-per-megawatt-hour trigger. The package also includes a bring-your-own-new-capacity requirement and a Cost Recovery Agreement intended to address the risk of shifting transmission costs to other customers.
ISO New England’s proposed implementation schedule identifies June 1, 2027, for the application and study process and June 1, 2028, for the new transmission services.
The filing gives FERC a detailed proposal to review, but the Commission must still determine whether the proposed tariff revisions adequately address the concerns raised in its June order.
CAISO’s flexible connection proposal reaches its filing date
California ISO’s Board of Governors approved its large-load reform package on October 28, following months of stakeholder discussions and revisions to the proposed tariff language.
The proposal includes a flexible interim connection pathway intended to allow eligible large electricity users to receive service while required transmission upgrades are still being completed. Instead of requiring every upgrade to be finished before a facility can connect, the approach would allow qualifying customers to operate under specified limitations.
The package also addresses technical operating requirements, load studies and the treatment of transmission costs associated with serving new customers.
CAISO’s stakeholder initiative lists November 16 as its planned FERC filing date. Board approval confirms that the proposal cleared an important regional decision-making stage, but it is not itself confirmation that the tariff submission has reached FERC.
MISO’s proposals focus on reliability and coordinated studies
MISO’s work addresses two practical challenges: ensuring large loads can operate reliably on the transmission system and studying new electricity demand alongside the generation intended to serve it.
In September, MISO filed proposed reliability requirements for large-load interconnections. These address the technical standards new facilities must meet when connecting to the grid.
The operator also proposed a Large Load Addition Resource Study process in October. The approach would allow electricity loads of at least 200 megawatts and associated generation resources to be studied at the same time, with each represented in the other’s system models. This is intended to improve coordination between new demand and the power resources being developed to supply it.
MISO and its transmission owners received a 90-day extension from FERC to continue their stakeholder process and prepare responses to the June show-cause order. In its November 16 Large Load Working Group status report, MISO listed its earlier reliability and study-related proceedings but did not identify a completed response filing in the show-cause docket.
PJM continues work on its large-load tariff changes
PJM’s response is being developed alongside a separate regulatory process addressing co-located generation and large loads.
The regional operator’s November 5 Special Members Committee agenda included further consultation on a proposed set of tariff filings to address FERC’s large-load show-cause order. A November 12 transmission-owner committee agenda also included proposed provisions concerning cost-recovery protections.
PJM’s process is particularly important because FERC is addressing its co-location framework in a separate proceeding. The June show-cause order focuses on other large-load connection issues, including how customers obtain transmission service and how associated infrastructure costs are handled.
The available records reviewed for this article did not establish that PJM’s full response had been filed by the November 16 deadline.
NYISO advances its proposal through stakeholder review
NYISO has followed a separate stakeholder process to develop its response. Its Management Committee considered the proposed reforms on November 2, with the package addressing large-load study procedures, transmission services and cost allocation.
The proposal also includes a state-exempt category for certain requirements that New York has not yet adopted, reflecting the region’s regulatory framework.
FERC granted NYISO and its transmission owners a 90-day extension in August, making November 16 the deadline for their responses or qualifying tariff filings. The available records reviewed for this article did not confirm a completed submission by the deadline.
SPP has four additional days
SPP is working to a November 20 deadline after FERC granted a 95-day abeyance rather than the 90 days granted to the other regions.
Its existing framework includes procedures for studying high-impact large loads and assessing generation intended to serve them. FERC’s show-cause order nevertheless identified additional issues for SPP to address, including the evaluation of alternative transmission technologies and requirements for documenting ongoing operating conditions.
SPP’s schedule includes an anticipated Board decision on November 17, ahead of its November 20 filing deadline.
FERC’s review will determine what changes take effect
The June show-cause orders gave the regional operators two routes: demonstrate that their existing tariffs are adequate or propose revisions under Section 205 of the Federal Power Act. A qualifying Section 205 filing can suspend the filing party’s separate obligation to respond under Section 206 while FERC considers the proposed changes.
The Commission’s orders are preliminary. They do not make final findings that the existing tariffs are unjust and unreasonable, nor do they impose new transmission rates.
Interested parties can submit comments within 30 days after each filing. FERC will then review the proposed changes and consider whether they address the concerns raised in the show-cause proceedings.
The filing process is the first concrete test of the solutions each region has developed. FERC gave the operators the opportunity to write their own tariff reforms; the proposals now submitted—or still to come—will show how each region intends to accommodate large new electricity users while addressing the costs and operating demands they bring to the grid.
The debate over how large electricity users connect to the grid comes as utilities also pursue major transmission projects to expand the power system’s capacity. In Virginia, Dominion Energy’s $873.6 Million Morrisville-to-Wishing Star Transmission Project Heads to Key Hearing is advancing through a State Corporation Commission review, with an evidentiary hearing beginning November 16. The proposed 500-kilovolt and 230-kilovolt lines illustrate the physical infrastructure investment taking place alongside FERC’s effort to reform the rules governing grid access, transmission services and the costs of serving major new electricity users.

Factsheet: U.S. grid connection to data centers rules revised
- Federal Regulator: Federal Energy Regulatory Commission (FERC)
- Legal Authority: Section 206 of the Federal Power Act
- Initial Orders Issued: June 18, 2026
- Operators Covered: PJM, MISO, SPP, CAISO, ISO New England and NYISO
- Main Response Deadline: November 16, 2026 (five operators)
- SPP Response Deadline: November 20, 2026
- Comment Period: 30 days after each filing
- Key Reform Areas: Large-load studies, transmission services, co-location, cost transparency and cost recovery.