Dominion Energy‘s proposed $873.6 million Morrisville-to-Wishing Star transmission project enters a critical regulatory phase today, November 16, as Virginia’s State Corporation Commission (SCC) begins an evidentiary hearing on the company’s plans to expand high-voltage electricity infrastructure across three Northern Virginia counties.
The hearing, scheduled to begin at 10 a.m. in Richmond, will examine Dominion’s application to construct a new 500-kilovolt (kV) transmission line between the Morrisville Substation in Fauquier County and the Wishing Star Substation near Arcola in Loudoun County. The proceedings also cover a new 230-kV transmission line, reconstruction of existing infrastructure and upgrades to substations along the corridor.
The SCC’s review will help determine whether Dominion receives the necessary authorization to proceed with the proposed facilities. The evidentiary hearing is scheduled to continue through November 20, with November 23 and 24 reserved if additional time is needed.
$873.6 Million Transmission Infrastructure Expansion
Dominion filed its application with the SCC on February 27, 2026, outlining a broader infrastructure program spanning Fauquier, Prince William and Loudoun counties.
The largest component is a new 36.6-mile overhead 500-kV transmission line, designated Line #5008, connecting the Morrisville and Wishing Star substations. Dominion proposes to support the line primarily with galvanized steel monopole structures.
The application also includes an approximately 8.1-mile, 230-kV transmission line between the Morrisville and Anderson Branch substations in Fauquier County. This component, designated Line #2464, will be constructed alongside existing transmission infrastructure.
Beyond the two new lines, Dominion proposes to rebuild or partially rebuild multiple existing 500-kV and 230-kV transmission lines, install equipment at existing substations and expand the Morrisville Substation.
The company estimates the overall project will cost approximately $873.6 million in 2025 dollars. Of that amount, $779.6 million covers transmission-related work, while another $94 million is allocated to station-related improvements.
Dominion targets December 31, 2030, for the project to enter service.
Existing Transmission Corridor Requires Additional Right-of-Way
One of the project’s significant infrastructure considerations is how Dominion intends to accommodate the additional transmission capacity along an already developed electricity corridor.
The company proposes to use the existing Morrisville-Wishing Star corridor wherever practical. However, the application identifies approximately 37.5 miles of total project corridor, including 17.9 miles entirely within existing rights-of-way, 14.3 miles requiring expanded rights-of-way and 5.3 miles involving new rights-of-way outside the existing corridor or other company property.
In areas requiring expansion, the proposed additional width ranges from 3 feet to as much as 230 feet. New greenfield rights-of-way would generally measure between 100 and 150 feet wide.
The project also involves replacing existing lattice transmission towers with newer monopole structures in portions of Loudoun County.
These changes have brought land use, property impacts and environmental considerations into the regulatory review.
Data Center Demand and Project Necessity Under Scrutiny
The proposed transmission expansion comes as Northern Virginia continues to experience substantial electricity demand associated with data center development.
Dominion maintains that the project is necessary to address reliability violations identified by PJM Interconnection during its 2022 and 2024 Regional Transmission Expansion Plan cycles. The company also cites future electricity demand and the need to maintain the reliability of the regional transmission system.
However, the relationship between data center growth and the proposed infrastructure has become a major issue in the proceedings.
Fauquier County, the Piedmont Environmental Council, the American Battlefield Trust and other participating parties have raised questions about the project’s necessity, routing and potential impacts.
The dispute also extends to who should ultimately bear the cost of transmission infrastructure associated with large electricity users.
In an October 28 ruling, the hearing examiner granted Dominion’s motion to strike certain portions of testimony addressing project cost allocation. However, testimony concerning the need for the project, the role of load growth and potential routing alternatives remained admissible.
The distinction leaves questions about the project’s underlying electricity demand and routing within the evidentiary record, while cost allocation itself is being addressed through a separate regulatory process.
Construction Targeted for 2027
Dominion’s current project schedule anticipates construction beginning in spring 2027, with completion targeted for summer 2030.
Today’s hearing represents an important step toward determining whether the proposed transmission facilities can advance to construction.
The SCC will consider the evidence presented during the proceedings before making its final decision. A hearing examiner is expected to prepare a report containing findings and recommendations for the commission.
For Dominion, approval would advance a major transmission investment intended to strengthen electricity delivery across parts of Northern Virginia. For the participating counties, property owners and conservation organizations, the proceedings provide an opportunity to challenge aspects of the proposed infrastructure before construction can proceed.
Grid operators to update the rules governing connections for data centers
The proposed $873.6 million transmission expansion comes as federal regulators push regional grid operators to update the rules governing connections for data centers and other large electricity users. FERC’s review of large-load tariffs across six U.S. grid regions is examining how new demand is studied, how transmission upgrades are funded and how utilities protect existing customers from bearing costs associated with major new connections. Dominion Energy’s Virginia project therefore forms part of a broader national challenge: building the transmission infrastructure needed to serve rising electricity demand while establishing who pays for it.

Morrisville-to-Wishing Star Transmission Project: Factsheet
- Developer: Dominion Energy Virginia
- Estimated Investment: $873.6 million
- Location: Fauquier, Prince William and Loudoun counties, Virginia
- New 500-kV Transmission Line: Approximately 36.6 miles
- New 230-kV Transmission Line: Approximately 8.1 miles
- Project Corridor: Approximately 37.5 miles
- Regulatory Docket: PUR-2026-00021
- Evidentiary Hearing: November 16, 2026
- Target Construction Start: Spring 2027
- Target Completion: Summer 2030
- Target In-Service Date: December 31, 2030