Uganda Standard Gauge Railway: $3B Financing Eyes January

Home » Transport » Rail » Uganda Standard Gauge Railway: $3B Financing Eyes January
Uganda Standard Gauge Railway

The Uganda Standard Gauge Railway is still waiting for its money. Works minister Fred Byamukama told Parliament on November 17 that the government is working toward financial close in January 2027 on the €2.7 billion ($3 billion) line from Malaba to Kampala. Full construction cannot start until then, two years after the contract was signed.

Where the Uganda Standard Gauge Railway financing stands

The money is arriving in pieces. The Islamic Development Bank has approved €650.75 million. Meanwhile, the OPEC Fund began appraising a €150 million loan on October 19 and is targeting board approval by November 30. In addition, export credit agencies have agreed in principle to lend, and talks with the African Development Bank continue. Citibank is helping to raise the funds.

The timetable has slipped. Treasury officials had earlier committed to financial close by November 2026, and the target is now January 2027. The minister said lender appraisals and environmental requirements should finish by December.

What is already in place

Early work is under way. Yapi Merkezi, the Turkish contractor, has carried out preparatory works worth €75 million under a limited notice to proceed issued in May 2025. Crews have also built a sleeper factory and construction facilities in Iganga, about 120 kilometres east of Kampala.

Land is the other big task. The government now holds 2,108 of the 3,536 acres it needs. As a result, the contractor has about 130 kilometres of corridor ready, just under half the line. Malaba to Mayuge is furthest along, with about 98% of a continuous corridor secured. However, landowners are still owed Shs472.45 billion, and the government has set aside Shs221 billion for compensation this financial year.

What happens next for the railway?

After financial close, the government will issue the full notice to proceed in early 2027. Yapi Merkezi’s contract gives it four years of construction from that green light. The minister said a reliable completion date can be set only after financial close.

The plan reaches well beyond Malaba. The government is also working on early stages of a further 1,425-kilometer extension to the north and southwest, linking South Sudan, the Democratic Republic of Congo, and Rwanda. Kenya is a risk to watch. Uganda’s line will connect to Kenya’s railway at Malaba, but Kenya still has to finance its own missing link between Naivasha, Kisumu, and Malaba. The story has a history. Uganda cancelled its earlier deal with a Chinese contractor in 2023 and signed with Yapi Merkezi in October 2024. Yapi Merkezi also built Tanzania’s 1,219-kilometer standard-gauge railway.

Uganda Standard Gauge Railway
The 272-kilometer line will link Kampala to Kenya’s railway and the port of Mombasa.

Other projects

Kenya and Uganda have launched the $943 million Phase 2C of the Naivasha-Kisumu-Malaba SGR extension project. Kenya’s President Dr. William Ruto and Uganda’s Yoweri Museveni presided over the groundbreaking ceremony. The move marks a monumental step toward strengthening regional transport and trade connectivity. President Ruto noted that the railway is a colonial infrastructure traversing Kenya from the Coast to the Western region and into Uganda.

Moreover, he noted that it has profoundly shaped the geography and economic trajectory of the nation. Once complete, Ruto notes that the railway will be fundamental in catalyzing trade and unlocking economic potential.

Both presidents are confident that this modern infrastructure will replicate and surpass that legacy by igniting new growth corridors. Also in attendance to the event was the Prime Cabinet Secretary Dr. Musalia Mudavadi and Cabinet Secretary for Roads and Transport Mr. Davis Chirchir. Uganda is also advancing its own end of the SGR as it inked $800 million financing with Saudi Arabia.

Fact Sheet

Project: Malaba to Kampala Standard Gauge Railway (first phase of a planned 1,700 km network)

Length: 272 km, electrified

Value: €2.7 billion (about $3 billion)

Contractor: Yapi Merkezi and YM Global joint venture (contract signed October 14, 2024)

Financing so far: Islamic Development Bank €650.75 million; OPEC Fund €150 million under appraisal

Financial close target: January 2027

Construction period: four years from full notice to proceed

Land acquired: 2,108 of 3,536 acres

Planned extension: 1,425 km to the north and southwest

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.