Project Factsheet for Outer Dowsing Offshore Wind Farm/Generating Station
DeveloperGT R4 Ltd. – a JV of TotalEnergies, Corio Generation and Gulf Energy Development
LocationSouthern North Sea, 54 km (33 mi) off Lincolnshire Coast in the UK
CapacityUp to 1,500 MW
TurbinesUp to 100 offshore wind turbines
Offshore InfrastructureTurbine arrays, offshore and onshore electrical substations, export cables.
Onshore ConnectionLandfall near Anderby Marsh, South Lincolnshire. Transmission to Surfleet Marsh substation will follow.
DCO DecisionGranted February 2026 by UK Department for Energy Security and Net Zero.
Examining Authority ReportSubmitted to Secretary of State 10 July 2025.
Economic Impact£2 billion investment. Thousands of UK jobs also projected over lifecycle.
Household Equivalent1.6 million UK homes powered annually.
Key StatutePlanning Act 2008
Project Stakeholders, Contractors and their Roles
GT R4 Limited/Outer Dowsing Offshore WindProject owner
TotalEnergiesPartner and lead energy developer
Corio GenerationJoint venture investor and developer
Gulf Energy DevelopmentCo-developer. Also supports technical and project delivery.
UK Department for Energy Security and Net ZeroDecision authority on DCO
Planning InspectorateLead examining authority that conducted statutory examination
National GridFuture system operator for onshore grid connection. Will also oversee transmission infrastructure.