Western Downs Digital Park: $32B Data Centre Wins Environmental Approval

Home » Buildings » Data Center » Western Downs Digital Park: $32B Data Centre Wins Environmental Approval

Project Factsheet

Project NameWestern Downs Digital Park (WDDP)

Location1933 Dalby-Kogan Road, Western Downs, Queensland (approx. 250 km west of Brisbane)

Estimated ValueA$31.9 billion (US$20.7 billion)

Site and Footprint801-hectare cattle feedlot site featuring four data centre buildings (approx. 36,000 sq m each)

Capacity1.44 GW of planned IT capacity (up to 2.16–3.24 GW peak power demand)

TimelineFour-stage rollout over 4 to 6 years, with initial operations slated to begin in 2027

EmploymentUp to 1,500 construction workers and 1,000 full-time operational jobs

Approval StatusFederal environmental clearance granted; awaiting local council and Foreign Investment Review Board (FIRB) approvals

Project Team

  • Developer and Operator: Zerra DC (Singapore-headquartered hyperscale platform backed by majority shareholder AGP)
  • Consortium Partners: Macquarie Capital (also serving as project and financial adviser) and Dexus (via Australian Data Centres)
  • Anchor Tenant: Anthropic (leading AI company behind Claude, committing to Stage 1 capacity)

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *