Project Factsheet: Columbia River Bridge Replacement
- Contract Estimate: $3.3 billion to $3.885 billion
- Corridor Estimate: Approximately $14.4 billion
- RFP Issued: Nov. 23
- Proposals Due: March 24, 2027
- Completion Target: Fourth quarter 2036
Project Team
- Administrator: Washington State Department of Transportation
- Partner: Oregon Department of Transportation
- Programme: Interstate Bridge Replacement, WA-OR joint
- Shortlisted JV: Columbia River Constructors
- JV Partners: Kiewit, Guy F. Atkinson, Traylor Bros
- Federal Reviewers: FHWA, FTA
Scope
- Two fixed-span bridges over Columbia River
- Light-rail-ready southbound bridge deck
- Shared-use path links two states
- Hayden Island and SR 14 interchange works
Project Highlights
- Progressive design-build delivery model
- $5.69 billion first funded phase
- $1 billion FTA grant pursuit
- Open-book pricing with cost estimator
Key Developments
- Final RFP published Nov. 23
- Sole JV advanced on Nov. 12
- Environmental review cleared July 1
- Small-business goals set at 16 and 19 percent
Key Challenges
- Single-bidder price negotiation risk
- Two-state traffic and utility coordination
- Permits and property needs remain
- Cost control across 2036 delivery
Outlook
- Proposals close March 24, 2027
- Winner named May 26, 2027
- Contract executes July 30, 2027
- Construction completes by late 2036