Project fact sheet
NamePORTS-Pike Technology Campus, also known as the Flagship project.
TypeLarge-scale artificial intelligence data center campus integrated with dedicated power generation and high-voltage transmission infrastructure.
LocationPortsmouth Site, Pike County, Ohio, United States, on former federal uranium-enrichment industrial land.
Estimated investmentApproximately $33 billion for the planned gas-fired generation program. The wider project also includes substantial data center and grid infrastructure investments.
Data center demandApproximately 10 GW of planned power load.
Generation capacityApproximately 10 GW of new generation, including 9.2 GW of natural gas-fired capacity.
Transmission infrastructureThree planned 765-kilovolt transmission lines and associated network upgrades.
Initial electricity supplyAn 800-megawatt phase under AEP Ohio’s data center tariff.
Study scopeAssessment of an additional 9.6 GW of load and approximately 10.2 GW of gas-fired generation under PJM’s study agreement.
Development scheduleGeneration and associated infrastructure planned in phases through 2032.
Regulatory authorityFederal Energy Regulatory Commission and Public Utilities Commission of Ohio, alongside PJM’s regional grid-planning processes.
Current statusPJM study agreement filed with FERC on October 13, 2026; final infrastructure decisions and cost-allocation arrangements remain subject to further review.
Funding commitmentsSB Energy has committed to funding required generation and power-delivery infrastructure, subject to the applicable arrangements and regulatory proceedings.
Grid benefitsThe project commitments include making excess generation and transmission capacity available to the wider electricity network.
Project team
SponsorSoftBank Group
Data center developerSB Energy
Electricity transmission developerAEP Ohio
Regional grid operatorPJM Interconnection
Federal land and site stakeholderU.S. Department of Energy
Federal regulatory authorityFederal Energy Regulatory Commission
State regulatory authorityPublic Utilities Commission of Ohio
Technology infrastructure partnerNVIDIA
Planned AI customerOpenAI