Project Overview
- Project Value: $10B
- Location: Richmond County, North Carolina
- Developers: Amazon & Duke Energy
- Project Name: Energy Way Tech Campus
- Status: Public hearing and permitting
Scope
- 21 data center buildings planned
- 1,600 MW of diesel backup generation
- Temporary power infrastructure by Duke Energy
- Air quality permits under review
Project Highlights
- Major hyperscale data center campus
- Supports long-term cloud expansion
- Significant utility infrastructure required
- One of the region’s largest investments
Community Concerns
- Air emissions from diesel generators
- Located in a vulnerable community
- Environmental and health concerns raised
- Public comments invited on permits
Key Developments
- Public hearing scheduled for July 30
- Comment period ends July 31
- State reviewing draft air permits
- Regulators classify facility as a minor pollution source
Outlook
- Permit approvals will shape project timeline
- Public feedback may influence final decisions
- Campus expected to boost regional investment
- Environmental scrutiny likely to continue