Project Factsheet:
- Project Name: TeraWulf Hyperscale Data Center Campus
- Location: Hancock County, Kentucky, USA
- Estimated Investment Value: $14 Billion
- Project Type: Hyperscale AI and high-performance computing data center
Timeline
- 2026: Development advancing and tenant negotiations ongoing
- Late 2026: Construction expected to begin
- Late 2027: Campus targeted to come online
Site & Scale
- Project Site: Former Century Aluminum smelter property
- Site Acquisition: $200 million property sale
- Estimated Site Development Cost: Up to $4 billion
- Future Tenant Investment: $10 billion+ in servers and hardware
- Campus Type: Large-scale hyperscale AI infrastructure facility
Project Teams
- Developer: TeraWulf
- Potential Tenants: Undisclosed hyperscale/AI computing operators
- Local Stakeholders: Hancock County officials and residents
Infrastructure Scope
- Redevelopment of former industrial smelter site
- Construction of hyperscale data center infrastructure
- High-performance computing and AI server deployment
- Large-scale electrical and utility infrastructure
- Supporting water and environmental management systems
Strategic Objectives
- Expand AI and high-performance computing capacity
- Position Kentucky as a data center hub
- Repurpose former industrial land for digital infrastructure
- Support large-scale cloud and AI workloads
- Drive regional economic development and investment
Challenges
- Strong local opposition over environmental concerns
- Concerns about electricity demand and water usage
- Questions about tax benefits and community impact
- Potential contamination concerns from previous industrial use
- Community criticism over lack of transparency and public engagement
Current Status
- Project moving forward despite mounting opposition
- More than 1,100 signatures gathered on opposition petition
- Tenant negotiations expected to conclude this year
- Construction remains scheduled to begin later in 2026




Leave a Reply