Project Fact Sheet
NameProject Infinity – Infinity Two
TypeCommercial nuclear fusion power plant
TechnologyStellarator fusion
Planned capacity400 MWe
Earlier planned capacity350 MWe
LocationTVA Bull Run Energy Complex, Clinton, Tennessee, USA
Site backgroundFormer TVA Bull Run fossil power plant
Development modelMulti-phase fusion development campus
First phaseInfinity One prototype and workforce training center
Infinity One targetCommissioning and startup in 2029
Infinity Two construction targetAs early as 2028
Full startup target2034
Regulatory approvalTennessee fusion-specific byproduct material license
License dateAugust 31, 2026
Regulatory frameworkTennessee Chapter 0400-20-14
Initial Project Infinity investmentReported $223 million for the initial deployment plan
Grid purposeBaseload electricity generation
Existing infrastructurePotential reuse of Bull Run industrial infrastructure
Research partnersOak Ridge National Laboratory and University of Tennessee
Commercial technology providerType One Energy
Project Team
Technology providerType One Energy
Utility partnerTennessee Valley Authority
State regulatorTennessee Department of Environment and Conservation
Federal nuclear regulatorNuclear Regulatory Commission
Research partnerOak Ridge National Laboratory
Academic partnerUniversity of Tennessee
Preliminary design engineeringAECOM
Manufacturing supportTVA Power Service Shops
Regulatory affairs and licensingType One Energy
SiteTVA Bull Run Energy Complex