Infinity Two fusion plant

Project Fact Sheet

NameProject Infinity – Infinity Two

TypeCommercial nuclear fusion power plant

TechnologyStellarator fusion

Planned capacity400 MWe

Earlier planned capacity350 MWe

LocationTVA Bull Run Energy Complex, Clinton, Tennessee, USA

Site backgroundFormer TVA Bull Run fossil power plant

Development modelMulti-phase fusion development campus

First phaseInfinity One prototype and workforce training center

Infinity One targetCommissioning and startup in 2029

Infinity Two construction targetAs early as 2028

Full startup target2034

Regulatory approvalTennessee fusion-specific byproduct material license

License dateAugust 31, 2026

Regulatory frameworkTennessee Chapter 0400-20-14

Initial Project Infinity investmentReported $223 million for the initial deployment plan

Grid purposeBaseload electricity generation

Existing infrastructurePotential reuse of Bull Run industrial infrastructure

Research partnersOak Ridge National Laboratory and University of Tennessee

Commercial technology providerType One Energy

Project Team

Technology providerType One Energy

Utility partnerTennessee Valley Authority

State regulatorTennessee Department of Environment and Conservation

Federal nuclear regulatorNuclear Regulatory Commission

Research partnerOak Ridge National Laboratory

Academic partnerUniversity of Tennessee

Preliminary design engineeringAECOM

Manufacturing supportTVA Power Service Shops

Regulatory affairs and licensingType One Energy

SiteTVA Bull Run Energy Complex

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *