£38.2bn Sizewell Point C Nuclear Plant Faces Major Setback as the Link Road Construction Slips

Home » Energy » Nuclear » £38.2bn Sizewell Point C Nuclear Plant Faces Major Setback as the Link Road Construction Slips
Sizewell Point C nuclear

Project fact sheet

ProjectSizewell C nuclear power station.

LocationSuffolk, England, United Kingdom.

Project typeNuclear power generation and supporting infrastructure.

Nuclear technologyTwo EPR reactors.

Planned capacityApproximately 3.2GW.

Baseline construction cost£38.2 billion.

Expected electricity generationFrom 2038.

Construction completion targetSummer 2039.

Planned operating lifeAt least 60 years.

Electricity supplyEquivalent to six million homes.

Final Investment DecisionJuly 2025.

Financing modelRegulated Asset Base model.

Sizewell Link Road length6.5km.

Two Village Bypass length1.8km.

Original road contractorGalliford Try.

Replacement contractorsKier and Breheny Civil Engineering.

Original road contract value£150–£200 million.

Reported additional design-related costApproximately £30 million.

Expected road delaySix months to one year.

Main purpose of roadsDivert construction traffic from nearby villages.

Wider transport measuresRail, sea freight and park-and-ride facilities.

Main reactor technology supplierEDF.

Project team

DeveloperSizewell C Ltd.

Government shareholderUK Government.

Nuclear partnerEDF

Investors:

Former road contractorGalliford Try

Road contractors:

  • Kier
  • Breheny Civil Engineering.

Government departmentDepartment for Energy Security and Net Zero.

Nuclear technologyEDF EPR.

Financing structureRegulated Asset Base model.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *