Project Overview

  • Project Name: Mary’s Creek Water Reclamation Facility
  • Owner: City of Fort Worth Water Department
  • Location: 11091 Chapin Road, west Fort Worth, Tarrant County, Texas
  • Project Type: Greenfield wastewater treatment and water reclamation plant
  • Contract Value: $537.9 million
  • Wider Program Cost: $710 million, including lift stations and force mains (EPA estimate)
  • Capacity: 10 million gallons per day initially; expandable to 15 million gallons per day (TWDB filings)
  • Treatment Technology: Membrane bioreactor with advanced nutrient removal
  • Buildings: Eight buildings, about 94,700 sq ft
  • Procurement: Competitive sealed proposals, issued April 2026
  • Contract Authorized: August 25, 2026
  • Construction Start: November 2026 (scheduled)
  • Target Completion: Summer 2030
  • Financing: $348 million EPA WIFIA loan; application for up to $60 million from the Clean Water State Revolving Fund
  • Population Served: 1.4 million (EPA estimate)
  • Jobs: About 2,147 (EPA estimate)

Project Team

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *