Project Overview
- Project Name: Mary’s Creek Water Reclamation Facility
- Owner: City of Fort Worth Water Department
- Location: 11091 Chapin Road, west Fort Worth, Tarrant County, Texas
- Project Type: Greenfield wastewater treatment and water reclamation plant
- Contract Value: $537.9 million
- Wider Program Cost: $710 million, including lift stations and force mains (EPA estimate)
- Capacity: 10 million gallons per day initially; expandable to 15 million gallons per day (TWDB filings)
- Treatment Technology: Membrane bioreactor with advanced nutrient removal
- Buildings: Eight buildings, about 94,700 sq ft
- Procurement: Competitive sealed proposals, issued April 2026
- Contract Authorized: August 25, 2026
- Construction Start: November 2026 (scheduled)
- Target Completion: Summer 2030
- Financing: $348 million EPA WIFIA loan; application for up to $60 million from the Clean Water State Revolving Fund
- Population Served: 1.4 million (EPA estimate)
- Jobs: About 2,147 (EPA estimate)
Project Team
- Owner: City of Fort Worth Water Department
- Contractor: Webber
- Contractor Parent: Ferrovial
- Federal Lender: U.S. Environmental Protection Agency, WIFIA Program
- State Financing Agency: Texas Water Development Board
- Discharge Permit Regulator: Texas Commission on Environmental Quality
- Downstream Diversion Partner: Tarrant Regional Water District
- Design Engineer: Not publicly disclosed