Project factsheet: Riot Platforms AI data center in Rockdale, Texas
- Project: 191 MW AI data center
- Location: Rockdale, Texas
- Developer: Riot Platforms
- Tenant: Unnamed leading frontier AI lab
- Facility: Build-to-suit Tier 3 data center
- Capacity: 191 MW of critical IT capacity
- Initial lease term: 20 years through June 2048
- Initial contract value: Approximately $9.1 billion
- Potential contract value: Approximately $16.1 billion if both five-year extensions are exercised
- Financing: $573 million interim financing facility from Morgan Stanley for initial development costs
- First delivery: 96 MW expected in December 2027
- Full deployment: 191 MW expected in June 2028
- Rockdale context: Riot has executed data center leases totaling 241 MW at the campus