The future of Atlantic Shores offshore wind farm in NJ after project 1 termination

Home » Energy » Wind power » The future of Atlantic Shores offshore wind farm in NJ after project 1 termination
The future of Atlantic Shores offshore wind farm in NJ after project 1 termination

In the latest development, the Atlantic Shores South offshore wind project is facing renewed regulatory uncertainty after the U.S. Army Corps of Engineers (USACE) confirmed on November 17, 2026, that it plans to review its previously issued approval for the development.

The move adds another challenge to the proposed 2,800MW offshore wind development, which comprises Atlantic Shores Project 1 and 2, approximately 8.7 miles off the New Jersey coast. The development had already suffered significant setbacks. These include the withdrawal of Shell from the Atlantic Shores joint venture in 2025 and the termination of Project 1’s Offshore Wind Renewable Energy Certificate (OREC) award by the New Jersey Board of Public Utilities in August 2025.

The latest federal review introduces further uncertainty over the project’s prospects. It however does not in itself constitute cancellation of the entire development. It also does not mean automatic revocation of the separate federal Construction and Operations Plan approval granted by the Bureau of Ocean Energy Management (BOEM) in October 2024 to the entire development.

Atlantic Shores 1 offshore wind project in New Jersey terminated

Reported August 13, 2025 -The Atlantic Shores Offshore wind power project 1 has been terminated by the New Jersey Regulator who cancelled the preliminary approval. This action did not come as a surprise as Atlantic Shores had in June asked the BPU to do so in the face of the Trump Administration’s relentless war on offshore wind power projects.

Unlike the Empire Offshore wind power project that resumed after a months suspension, Atlantic has been unable to weather the storm. The project was one of the largest offshore wind farm projects in the USA.

Most recently another nail was hammered into the coffin when the Trump Administration paused any hope of further work on the project citing national security concerns.

On 21st August, Duke Energy halted its offshore wind plans off North Carolina that hoped to develop 2,400 megawatts of offshore wind capacity by 2035. This signals harsh times for offshore wind projects in general in the USA. This was followed by August 23 report that the Trump Administration had issued a stop order on the construction of Ørsted’s Revolution Offshore Wind project located off Rhode Island a move that could herald another casualty on a project that is almost complete.

The release of IRS Notice 2025-42, which clarifies how wind and solar projects will be treated under the One, Big, Beautiful Bill Act (OBBBA), the new Credit Termination Rules may be a lifeline for the Atlantic Offshore wind power project if it is able to meet the tight requirements for federal support.

The future of Atlantic Shores offshore wind farm in NJ after project 1 termination

Atlantic Shores Project 1 and 2 Proposed Offshore New Jersey

October 2024 – Atlantic Shores Offshore Wind is proposing the construction and operation of two distinct offshore wind energy projects dubbed Atlantic Shores Project 1 and 2. Combined, the COP approves up to 195 total wind turbine generators. The first facility holding between 105-136 wind turbine generators and between 64-95 wind turbine generators for the second facility. The wind turbine area for both sites will total 102,124 acres (413.3 km2).

The projects will also have up to 10 offshore substations (also called “electrical service platforms”), one meteorological tower, up to four temporary meteorological and oceanographic buoys inter-array cables, up to two onshore substations, one operations and maintenance facility, and up to eight transmission cables making landfall at two New Jersey locations: the Atlantic Landfall site in Atlantic City, and Monmouth Landfall site in Sea Girt.

The wind turbine generators, offshore substations, array cables, and substation inter-connector cables will be located approximately 8.7 miles from the New Jersey shoreline at is closest point.

Environmental considerations have also been part of the approval process. According to BOEM, strategic measures have been put in place to mitigate impacts on marine life and other ocean activities. As the project constructor, Atlantic Shores Offshore Wind is expected to align its activities – during the course of the project – in accordance with specifications provided in the BOEM’s environmental review for the project.

Also Read: Maine Floating Offshore Wind Energy Project

Atlantic Shores Offshore Wind Receives Construction and Operations Plans (COP) Approval from BOEM

Atlantic Shores Offshore Wind announced that it has received Construction and Operations Plans (COP) approvals from the Bureau of Ocean Energy Management (BOEM) for Atlantic Shores Project 1 and 2.

The two projects combined will generate enough energy, of up to 2,800 megawatts of clean renewable energy, that will serve more than a third of the more than 3 million New Jersey homes.

The energy produced is an up-step to what was originally proposed in 2021 before the project stalled after Netherlands-based Ørsted, a wind farm developer, pulled out of the project. The originally proposed energy production was up to 1,510 megawatts.

According to Joris Veldhoven, Chief Executive Officer, Atlantic Shores Offshore Wind, construction that is to start in 2025 will be a huge leap in helping New Jersey achieve 100% clean energy by 2035. “Securing these critical approvals enables New Jersey’s first offshore wind project to start construction next year and represents meaningful progress in New Jersey achieving 100% clean energy by 2035 . . .”

Benefits of the Atlantic Shores Project 1 and 2

The construction of the Atlantic Shores Project 1 and 2 will also have other upsides. Other than the production of clean renewable green energy, it will also support climate action and sustainable energy goals. This will include: job creation for the people of New Jersey, and an economic boom off low-cost energy, as put by Senator George Helmy. “I believe that offshore wind has the potential to play a key role in transitioning us to a clean energy economy. Wind energy also has the potential to deliver zero-carbon energy to our state. This is while spurring billions of dollars in economic investment and creating good-paying jobs.”

If successful as per the projected specifications, it will be the largest offshore wind farm in the US, with the contractor expecting the project to be operational by 2028.

Also Read: New York City launches construction of the largest dedicated offshore wind port in the USA

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *