Core Scientific’s AI Data Center in Denton, Texas: Project Fact Sheet
Project Overview
Location8171 Jim Christal Road, Denton, Texas
ProjectConverting Bitcoin mining facility to AI data center
Investment Details
Projected Investment$6.1 billion
Land Lease78.85 acres of city-owned land
Power Access394 megawatts
Economic Projections
Estimated Property Tax Revenue$194 million (10 years)
Projected Employment300 people
Core Scientific’s data center in Denton: Project Timeline
Planned Completion2027
Read also$2B Central Ohio Data Center Campus: Expected to Cover 1.5 Million Sq. Ft.