Core Scientific’s 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal

Home » Buildings » Data Center » Core Scientific’s 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal
Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal

The Oklahoma data center is designed to deliver 70 MW of critical IT capacity for NVIDIA GPU computing, forming part of CoreWeave‘s 500-MW hosting agreement with Core Scientific.

Core Scientific’s 100-megawatt high-performance computing data center in Muskogee, Oklahoma, is advancing as the company expands its infrastructure for artificial intelligence workloads under a multibillion-dollar hosting agreement with CoreWeave.

The facility, being developed at Port Muskogee, is designed to accommodate NVIDIA GPU infrastructure for CoreWeave and an undisclosed end customer. Of its 100 MW total power capacity, approximately 70 MW will serve critical IT equipment, with the remaining 30 MW allocated to cooling, electrical systems and other supporting infrastructure required to operate the computing equipment.

The Muskogee facility forms part of a broader 500 MW hosting agreement between Core Scientific and CoreWeave. The agreement carries a potential value of approximately $8.7 billion over 12-year contract terms, with each contract offering two five-year extension options. The 100 MW development in Muskogee accounts for part of the computing capacity Core Scientific has committed to provide under the wider arrangement.

Construction, Data Hall Configuration and Power Infrastructure

Construction of the Muskogee facility began in the first quarter of 2025. With substantial completion initially anticipated in the first half of 2026, according to Core Scientific’s project disclosures. Evans General Contractors is serving as construction manager under a cost-plus-fee contract with a guaranteed maximum price, subject to adjustments.

The project design includes two compute data halls and a separate network data hall. Together, these facilities will accommodate high-density GPU equipment and the networking systems needed to run high-performance computing (HPC) workloads.

The data center will require 100 MW of power, including approximately 70 MW for its IT equipment. The remaining 30 MW will support cooling, electrical distribution and other systems that keep the GPU infrastructure operating.

Project disclosures identify Oklahoma Gas and Electric Company as the electricity provider under an electric service agreement. The arrangement connects the development to the local power grid and establishes the utility’s role in supplying electricity to the facility.

CoreWeave’s 500-MW Hosting Agreement

The Muskogee data center is one component of CoreWeave’s wider 500 MW hosting arrangement with Core Scientific, which is supplying data center infrastructure for the AI cloud provider’s computing operations.

The broader agreement carries a potential contract value of $8.7 billion across 12-year contracts, each with two additional five-year renewal options. The contract value reflects the wider hosting arrangement and should not be attributed solely to the Muskogee facility.

CoreWeave will deploy NVIDIA GPU infrastructure at the Oklahoma site for an undisclosed customer. The companies have not publicly identified the end customer or detailed the specific AI workloads planned for the facility.

The development highlights the infrastructure requirements behind AI cloud computing, where GPU deployments require substantial electricity capacity, specialized cooling systems, networking equipment and purpose-built data center space.

$4 Billion Investment and 150 Jobs Projected

Port Muskogee estimates the development will generate more than $4 billion in capital investment and approximately $182 million in net economic benefits over the life of the project.

The facility is expected to support 150 jobs, with average salaries exceeding $65,000. Local public institutions, including Muskogee County, Hilldale School District and the City of Muskogee, could receive more than $12 million in property and sales tax revenue from the development.

The projections position the project among the major infrastructure investments planned for the Muskogee area. The data center could boost local economic activity through construction, operations, job creation and tax revenues.

Core Scientific’s Broader Muskogee Expansion

The 100-MW facility forms part of Core Scientific’s broader expansion into high-performance computing and AI infrastructure, as the company builds out data center capacity for customers requiring large-scale GPU computing.

Core Scientific has pursued additional infrastructure and power capacity in Muskogee, extending the site’s significance beyond the original CoreWeave development. The location is emerging as part of the company’s broader HPC strategy. Which involves converting and developing infrastructure to serve AI and cloud computing demand.

The Muskogee project brings together data center construction, utility infrastructure, GPU deployment and long-term hosting contracts, illustrating how the growth of AI computing is driving new investment in large-scale digital infrastructure across the United States.

The Muskogee development is part of a wider US AI infrastructure buildout, as developers race to secure power and computing capacity for increasingly large AI workloads. That expansion is also taking shape in New Mexico, where Oracle’s $165 billion Project Jupiter is planned as a massive AI data center campus, highlighting the scale of investment now flowing into power-intensive data center construction and the infrastructure needed to support next-generation AI computing.

Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal
Core Scientific’s 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal

Project Factsheet: Core Scientific Muskogee AI Data Center

  • Project name: Core Scientific Muskogee High-Performance Computing (HPC) Data Center
  • Location: Port Muskogee, Muskogee, Oklahoma, USA
  • Project type: AI and high-performance computing data center
  • Developer: Core Scientific
  • HPC tenant: CoreWeave
  • End customer: Undisclosed
  • Total facility capacity: 100 MW
  • Critical IT load: Approximately 70 MW
  • Supporting infrastructure capacity: Approximately 30 MW for cooling, electrical systems and other ancillary infrastructure
  • GPU infrastructure: NVIDIA GPUs
  • Facility configuration: Two compute data halls and one network data hall
  • Construction manager: Evans General Contractors
  • Electricity provider: Oklahoma Gas and Electric Company
  • Construction start: First quarter of 2025
  • Original substantial completion target: First half of 2026
  • Hosting agreement: Part of CoreWeave’s 500 MW HPC hosting agreement with Core Scientific
  • Potential contract value: $8.7 billion across the broader hosting agreement
  • Contract duration: 12 years, with two five-year extension options per contract
  • Capital investment: More than $4 billion projected
  • Projected employment: 150 jobs
  • Projected average salaries: More than $65,000
  • Projected local net economic benefits: Approximately $182 million over the life of the project
  • Projected property and sales tax revenue: More than $12 million
  • Local beneficiaries: Muskogee County, City of Muskogee and Hilldale School District

The $8.7B potential contract value applies to the broader CoreWeave–Core Scientific hosting arrangement, not solely the Muskogee facility. Economic, employment and tax figures are projections. The first-half 2026 completion date was the original disclosed target and is not independent confirmation of operational status.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.