Crusoe Abilene AI Data Center Campus: Project Factsheet
LocationLancium Clean Campus, south of Abilene, Texas
Total Site Area~800 acres
Primary Use CaseLarge-scale AI model training and generative AI workloads
Total Facility Size~4 million square feet (upon completion)
Development Phases
Phase 1 – Initial Build
TimelineOperations expected early 2025
Capacity200 MW electrical capacity
Facility Size~980,000 square feet across two buildings
GPU DeploymentUp to 100,000 NVIDIA GB200 (Blackwell) GPU server nodes

Phase 2 – Expansion
TimelineFull buildout projected mid-2026
Facility AdditionSix additional data halls
GPU DeploymentUp to 300,000 additional NVIDIA Blackwell GPUs
Total CampusEight high-performance data halls
Crusoe AI Data Center Campus in Abilene Technical Specifications
Cooling SystemDirect-to-chip liquid cooling with closed-loop, zero-water-evaporation technology
Per Building CapacityUp to 50,000 NVIDIA GB200 GPU server nodes
Power InfrastructureDesigned for hyperscale AI workloads with advanced power distribution
ConnectivityHigh-bandwidth networking optimized for distributed AI training
Total Project Capital
Current Commitment (May)~$15 billion
Recent Funding Round$11.6 billion in debt and equity
Previous Funding$3.4 billion (initial phases)
Timeline Milestones
October 2024$3.4 billion build-to-suit agreement announced
Early 2025Phase 1 operations commence
May 2025$11.6 billion additional funding secured
Mid-2026Full 8-building campus completion projected
Read also: Google Plans $10 Billion Data Center Campus in West Memphis, Arkansas
The rapid expansion of AI infrastructure is also driving proposals for large data center campuses beyond Texas. In Georgia, Eatonton 379, LLC has proposed a 3.5-million-square-foot campus with up to 520 MW of estimated peak electrical demand in Putnam County, targeting completion in 2031. The project still requires local land-use approvals, and its power-supply arrangements remain unconfirmed.