Doicesti SMR Project in Romania Faces Setback as More Than 80% of FID Conditions Remain Unmet

Home » Energy » Nuclear » Doicesti SMR Project in Romania Faces Setback as More Than 80% of FID Conditions Remain Unmet
North Dakota Nuclear Power Plan Advances Through Statewide Feasibility and Siting Study

Doicesti Small Modular Reactor (SMR) Power Plant Project Fact Sheet

LocationDoicesti, Dambovita County, Romania

SiteFormer Doicesti coal-fired power station

Project companyRoPower Nuclear

Project shareholdersNuclearelectrica (50%) and Nova Power & Gas (50%)

Reactor technology providerUS-based NuScale Power

Reactor designNuScale VOYGR-6

Planned configurationSix NuScale Power Modules

Planned gross installed capacity462 MWe

Gross capacity per module77 MWe

Reactor typeSmall modular pressurized water reactor

Project development and engineering

Project launchSeptember 2022

Phase 1 FEEDConducted by NuScale and RoPower Nuclear

Phase 2 FEEDLed by Fluor Corporation and completed in late 2025

Site preparationActivities associated with the former coal station site have included demolition and site preparation by Nova Power & Gas and its wider group.

Final Investment Decision (FID)Approved by Nuclearelectrica’s shareholders in February 2026.

Construction start dateNot confirmed

Commercial operation dateEarlier project plans targeted operation in the early 2030s.

Current project status as of October 2026

StatusUnder reassessment

Outstanding investment conditionsMore than 80% unmet

NuScale framework agreementFinal terms remain unresolved.

Module purchase agreementBinding commitments covering the proposed six modules remain unresolved.

Performance and financial risk agreementNegotiations have not established the required binding purchase and reimbursement arrangements.

Site issueNatural gas identified around an old Soceram well has affected the site authorization process.

Independent site studyPreliminary results were expected in March 2027, with a final report expected in October 2027.

Proposed cost reductionsNuclearelectrica has proposed reducing RoPower’s spending and workforce while the project is reassessed.

Potential technology alternativesNuclearelectrica intends to compare available US-origin SMR technologies and alternative generation scenarios.

Project team and stakeholders behind Doicesti SMR Power Plant Project

RoPower Nuclear – Doicesti SMR project developer

Nuclearelectrica (SNN) – State-owned nuclear energy company and 50% RoPower shareholder.

Nova Power & Gas – Private energy company and 50% RoPower shareholder.

NuScale Power – Selected SMR technology provider.

Fluor Corporation – Engineering partner that led Phase 2 FEED.

U.S. Trade and Development Agency (USTDA) – Supported early project preparation through technical assistance.

CNCAN – Romania’s nuclear regulatory authority.

Romanian Ministry of Energy

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *