Project Fact Sheet
Project NameDemocratic Republic of Congo US$15 Billion Infrastructure Investment Programme
Project TypeNational transport and infrastructure development programme
LocationDemocratic Republic of Congo, Central Africa
Total Investment PitchApproximately US$15 billion
Main Railway ProjectDilolo–Sakania railway rehabilitation and modernisation
Railway InvestmentUS$1.258 billion government estimate; approximately US$1.8 billion expected investment reported by Mota-Engil
Railway Length1,004.5 kilometres according to government documents; approximately 1,037 kilometres according to Mota-Engil
Developer/ConcessionaireMota-Engil Africa for the Dilolo–Sakania concession
Parent CompanyMota-Engil SGPS, Portugal
Concession Period30 years
Project StatusRailway concession signed on August 26, 2026; rehabilitation and modernisation programme to be implemented
Freight Capacity TargetUp to 13.7 million tonnes annually
Construction EmploymentNot publicly disclosed
Permanent EmploymentNot publicly disclosed
TechnologyRailway track rehabilitation, modernisation, freight operations and supporting railway systems. Detailed technical specifications have not been published.
Raw Material SupplyCopper, cobalt and other minerals from the DRC’s mining regions will form an important part of the railway’s freight market.
Additional InfrastructureKwala and Kasumbalesa dry ports, Kalemie industrial port, Kinshasa–Brazzaville road-rail bridge, airport modernisation and additional railway connections.
Key Infrastructure RequirementsRailway tracks, signalling, locomotives, freight wagons, maintenance facilities, port terminals, cargo-handling equipment and logistics hubs.
Economic ImpactImproved mineral exports, lower transportation constraints, regional trade expansion, technology transfer and increased opportunities for local construction companies.
Primary Target MarketsInternational copper and cobalt markets, regional industrial supply chains, agricultural trade and Central African logistics networks.
Delivery RisksFinancing gaps, land acquisition, security concerns, cross-border coordination, engineering challenges and implementation capacity.
Expected CompletionNo definitive completion date for the entire US$15 billion programme has been announced.
Project Team
Government of the Democratic Republic of Congo– National infrastructure programme sponsor.
Jean-Pierre Bemba– Deputy Prime Minister and Minister of Transport, Democratic Republic of Congo.
Mota-Engil Africa– Concessionaire responsible for financing, rehabilitation, modernisation, operation and maintenance of the Dilolo–Sakania railway.
Mota-Engil SGPS– Parent company of Mota-Engil Africa.
Agency for the Monitoring, Coordination and Follow-up of Collaboration Agreements (APCSC) – Government agency responsible for monitoring and coordinating collaboration agreements.
Africa Finance Corporation (AFC)– Infrastructure development partner involved in the Lobito Corridor and proposed Banana–Boma–Matadi–Kinshasa railway.
US International Development Finance Corporation (DFC)– Financier of the Angolan railway section of the Lobito Corridor.
Development Bank of Southern Africa (DBSA)– Financier of the Angolan railway section of the Lobito Corridor.