Project Fact Sheet
Name: Drax Power Station Data Centre Development.
Location: Drax Power Station, near Selby, North Yorkshire, England, United Kingdom.
Type: Artificial intelligence data centre and digital infrastructure development.
Estimated total investment: More than £20 billion.
Initial phase investment: Approximately £2.5 billion.
Overall planned capacity: More than 1GW.
Phase One:
Capacity: Up to 100MW.
Target operational date: First quarter of 2028.
Phase Two capacity: Additional 500MW targeted between 2028 and 2031.
Phase Three: Additional capacity planned beyond 2031.
Site area: Approximately 1,000 acres.
Existing grid access: 4GW.
Existing active dispatchable generation: 2.6GW.
Main construction components: Data halls, cooling infrastructure, electrical plant buildings, offices and logistics facilities.
Initial electricity supply: Direct electricity imports from the national grid.
Potential subsequent electricity supply: Existing Drax generation through behind-the-meter arrangements, subject to approvals.
Planning authority: North Yorkshire Council.
Planning status: Initial planning application under preparation.
Public consultation deadline: December 3, 2026.
Key outstanding requirements: Planning permission, regulatory approvals, network approvals, anchor customer commitments and final investment decisions.
Project Team
Developer and site owner: Drax Group plc.
Strategic development partner: Brookfield.
AI infrastructure development partner: Radiant, Brookfield’s UK-headquartered AI infrastructure platform.
Investment and operating vehicle: Brookfield-Qai AI infrastructure joint venture.
Project executive: Will Gardiner, Chief Executive Officer, Drax Group.
AI infrastructure leadership: Mahdi Yahya, Chief Executive Officer, Radiant.
Land and site infrastructure: Drax Group.
Power integration and planning: Drax Group.
Data centre design and commercialisation: Radiant.
Customer engagement and anchor tenant procurement: Radiant.
Investment capital and operating capabilities: Brookfield-Qai.
Planning and regulatory authority: North Yorkshire Council and relevant UK government agencies.
Community engagement: Drax Group and its development partners.