Project Fact Sheet
Project NamePantheon AI Data Centre Campus
DeveloperPantheon Atlas LLC
LocationTopusko, Croatia
Total Investment Value€50 billion ($58.5 billion)
Initial Phase Investment€12 billion
Construction Start2027
Operations StartQ1 2029
Core CapacityHyperscale AI data center campus
Power Infrastructure500MW on-site solar plant
Energy Storage2GW / 8GWh BESS system
Solar Developer PartnerGreenvolt (LOI signed)
Grid InfrastructureFour 400kV transmission lines
Grid Capacity ImpactUp to 5.2GW additional renewable integration
Energy ModelBehind-the-meter renewable + storage system
Primary FunctionAI computing, cloud infrastructure, high-performance data processing
Development PhaseEarly construction planning and financing mobilization
Project Team
Project Owner / DeveloperPantheon Atlas LLC
Founding Partner / Strategic LeadJako Andabak
Lead Investment GroupTransatlantic institutional investment consortium
Renewable Energy PartnerGreenvolt (Portugal-based independent power producer)
Engineering & Technical Development:
- Pantheon AI internal engineering division (system architecture and AI infrastructure design)
- Hyperscale data center engineering specialists (gigawatt-scale facility design)
- Energy storage system designers (2GW/8GWh BESS integration)
- Transmission infrastructure engineers (400kV grid expansion design)
Government & Regulatory Authorities:
- Government of the Republic of Croatia
- Ministry of Economy and Sustainable Development
- Ministry of Physical Planning, Construction and State Assets
- Croatian Energy Regulatory Agency (HERA)
- HOPS – Croatian Transmission System Operator
- Sisak-Moslavina County authorities
- Municipality of Topusko
Financial & Legal Advisory:
- International legal advisory firms (cross-border structuring and compliance)
- Big Four consultancy firms (financial modelling, ESG, audit, and tax advisory)
- Infrastructure finance advisors (capital structuring and risk allocation)
- ESG and sustainability consultants (EU environmental compliance and reporting)
Infrastructure & Ecosystem Partners:
- Končar Group (electrical infrastructure and grid equipment systems)
- Croatian national grid operators (transmission and integration support)
- Renewable EPC contractors (solar and storage deployment)
- Telecom and fiber operators (high-capacity connectivity infrastructure – to be confirmed)
- Data center systems integrators (cooling, redundancy, and facility systems – to be confirmed)




Leave a Reply