Project Fact Sheet

NameEquinix Dallas 12 (DA12)

TypeData center

Location1550 West Mockingbird Lane, Dallas, Texas, USA

Developer and OperatorEquinix

Original Announced InvestmentApproximately $835 million

Combined Registered Construction PackagesApproximately $836.5 million

Main Construction Package$542.8 million

Interior Fit-Out Package$293.7 million

Building Area372,517 square feet

Interior Fit-Out Area158,293 square feet

Number of FloorsFour

Planned Power Capacity67MW

Backup Power20 generators

Construction StartFebruary 2026

Main Building CompletionOctober 2027

Interior Fit-Out CompletionMarch 2028

Current StatusUnder construction

Project Team

Developer and OperatorEquinix

ArchitectMargulies Hoelzli Architecture

Main Construction ContractorNot disclosed

Mechanical and Electrical ContractorsNot disclosed

Generator SupplierNot disclosed

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *