Project Overview
Joint venture between Orlen and Northland Power.
1.2 GW capacity offshore wind farm in the Polish Baltic Sea.
Nearly 50% of monopiles and transition pieces installed.
Van Oord’s Svanen vessel used for monopile installation.
First-ever transition pieces in Polish Baltic waters.
Subsea cables and offshore substation pylons set for installation next.
Domestic production in cities like Szczecin, Gdynia, and Bydgoszcz.
O&M base in Łeba opened in May 2025.
Commissioning in 2026, powering 1.5 million homes (3% of Poland’s demand).
Future expansion planned to 5.5 GW, including Baltic East project.
Also Read Vestas to establish offshore wind blade factory in Poland
Baltic Power Offshore Wind Farm Timeline
Pre-2023
Development and environmental permits secured.
Geotechnical and marine surveys completed.
Final turbine supplier (Vestas) confirmed.
2023-2024
Procurement and fabrication of monopiles and substations.
Construction logistics established at Port of Leba and Port of Gdynia.
Financing agreements finalized.
February 2025
Offshore construction begins with installation of first monopile foundations.
May 2025
Operations and maintenance (O&M) base inaugurated in Leba.
Transition pieces installed. Subsea cabling preparations also start.
July 2025
First 15 MW offshore wind turbine installed. This marked a major milestone.
Late 2025, 2026 onward
Progressive installation of remaining turbines and full grid connection.
Commissioning and commercial operations targeted for completion by late 2026.