Fact sheet: Oracle’s $165B Project Jupiter
- Project name: Project Jupiter
- Location: Santa Teresa, Doña Ana County, New Mexico
- Developers: Oracle, OpenAI; part of Stargate initiative
- Total investment: ~$165 billion
- Site size: ~1,400 acres
- Primary power: Bloom Energy fuel cells (natural gas)
- Fuel supply: Green Chile Natural Gas Pipeline
- Pipeline capacity: Up to 400 million cubic feet per day
- Pipeline length: ~17–18 miles
- Renewables pledge: Up to 2 GW to match emissions
- Construction status (Sept. 22, 2026): 26% complete (site); 10% (microgrid)
- Target compute delivery: First half of 2027
- Pipeline in-service date: Feb. 1, 2027 (delayed from Aug. 15, 2026)
- Key permits: Air-quality permit; emergency water withdrawal permit
- Financing: ~$18 billion in syndicated loans (trading at 89–91 cents)
- Local oversight: Project Jupiter oversight committee (Doña Ana County)
- Key opponents: New Energy Economy; Center for Biological Diversity