How is Oracle’s $165B Project Jupiter: On Track or Derailed?

Home » Buildings » Data Center » How is Oracle’s $165B Project Jupiter: On Track or Derailed?
How is Oracle’s $165B Project Jupiter: On Track or Derailed?

Fact sheet: Oracle’s $165B Project Jupiter

  • Project name: Project Jupiter
  • Location: Santa Teresa, Doña Ana County, New Mexico
  • Developers: Oracle, OpenAI; part of Stargate initiative
  • Total investment: ~$165 billion
  • Site size: ~1,400 acres
  • Primary power: Bloom Energy fuel cells (natural gas)
  • Fuel supply: Green Chile Natural Gas Pipeline
  • Pipeline capacity: Up to 400 million cubic feet per day
  • Pipeline length: ~17–18 miles
  • Renewables pledge: Up to 2 GW to match emissions
  • Construction status (Sept. 22, 2026): 26% complete (site); 10% (microgrid)
  • Target compute delivery: First half of 2027
  • Pipeline in-service date: Feb. 1, 2027 (delayed from Aug. 15, 2026)
  • Key permits: Air-quality permit; emergency water withdrawal permit
  • Financing: ~$18 billion in syndicated loans (trading at 89–91 cents)
  • Local oversight: Project Jupiter oversight committee (Doña Ana County)
  • Key opponents: New Energy Economy; Center for Biological Diversity

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *