Project Fact Sheet
ProjectHuawei 3D Data Center
LocationWuhu, Anhui, China
TypeArtificial intelligence data center
Capacity targetMore than 100,000 Ascend cards
Building power capacityUp to 168MW per facility, according to Huawei
ArchitectureFour-layer vertical data-center configuration
Cooling infrastructureDedicated cooling layer
Computing infrastructureDedicated IT equipment layer
Power infrastructureDedicated power supply layer
Backup systemsRoof-level backup power and battery systems
Construction approachLayered, modular and vertically stacked infrastructure
Launch dateSeptember 15, 2026
Construction costNot publicly disclosed
Design resourcesHuawei 3D Data Center Overview Design Library
Strategic purposeSupport large-scale AI supernode clusters
Project Team
Developer and technology providerHuawei Technologies
Cloud infrastructure operatorHuawei Cloud
Location partnerWuhu, Anhui, China
Architecture developmentHuawei data-center engineering teams
Data-center operations contributionHuawei Cloud Data Center Operations Department
Mechanical and electrical design contributionHuawei Infrastructure, Electromechanical and HVAC Design Management Department
Industry collaborationGlobal Computing Consortium and participating AIDC industry partners
Conference organizerGlobal Computing Consortium
Conference co-organizersChina Electronics Standardization Institute and China Electronics Engineering Design Institute Co., Ltd.