Project Fact Sheet
NameCôte d’Ivoire National Data Center.
LocationCôte d’Ivoire, with construction taking place within the country’s technology infrastructure network.
PurposeEstablish the country’s first state-owned national data center.
Wider programme value$170 million.
Data center financing$66.1 million EXIM guarantee.
Financing institutionExport-Import Bank of the United States (EXIM).
Financing programmeChina and Transformational Exports Program.
Construction statusConstruction has progressed beyond 20%.
Foundation stoneDecember 14, 2023.
Main objectiveStrengthen Côte d’Ivoire’s digital sovereignty and cybersecurity.
Planned capabilityDomestic hosting, storage and protection of government data.
Wider componentsGovernment digitization platform and intelligent border surveillance system.
Technology focusSecure digital infrastructure supporting government services and future digital workloads.
Expected opening2027, according to September 2026 reporting.
Strategic importanceSupports Côte d’Ivoire’s ambition to become a major West African digital hub.
Project Team
Government clientGovernment of Côte d’Ivoire.
Digital authorityMinistry of Digital Transition and Digitalization.
Lead Technology CompanyCybastion.
Financing institutionExport-Import Bank of the United States (EXIM).
Networking technology partnerCisco.
Infrastructure technology partnerHewlett Packard Enterprise.
Data center technology partnerSchneider Electric.
Construction partnerPORTEO Group.
Technical studies supportNational Bureau of Technical Studies and Development (BNETD-APL).
Financing programmeEXIM China and Transformational Exports Program.
Financial partnerCitibank.
US technology consortiumCybastion and participating American technology companies.




Leave a Reply