$10bn River Bend Data Center: Hut 8’S 330 MW Project Advances toward 2027 Operations in Louisiana

Home » Buildings » Data Center » $10bn River Bend Data Center: Hut 8’S 330 MW Project Advances toward 2027 Operations in Louisiana
Jacobs Selected as EPCM Contractor for Hut 8’s River Bend Data Center in Louisiana

Project fact sheet

Project nameRiver Bend Data Center

LocationWest Feliciana Parish, Louisiana, USA

DeveloperHut 8

Project valueUp to $10 billion (Phase One)

Project typeArtificial intelligence hyperscale data center campus

Status (2026)Under construction

Expected operationsSecond quarter of 2027

Site area592 acres (within a larger 2,361-acre optioned footprint)

Initial utility capacity330MW

Commercialized IT capacity245MW

Potential expansion capacityMore than 1GW

Construction jobsApproximately 1,000 during Phase One

Permanent operational jobs75+

Additional indirect jobsMore than 190

Primary applicationAI training, high-performance computing and cloud infrastructure

Major commercial agreement15-year AI infrastructure lease with Fluidstack for Anthropic

Project team

Project owner and developerHut 8

Anchor customerFluidstack

AI end userAnthropic

Strategic technology supporterGoogle

Electric utilityEntergy Louisiana

Engineering, procurement and construction managementJacobs

Digital infrastructure partnerVertiv

State partnerState of Louisiana

Economic development partnerLouisiana Economic Development (LED)

Local authorityWest Feliciana Parish Government

Financial partnersInstitutional bond investors supporting Hut 8’s $3.25 billion financing, with underwriting led by major financial institutions.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *