Jansen Potash Project Stage 2 Fact Sheet
LocationSaskatchewan, Canada
DeveloperBHP Group
CommodityPotash (fertilizer)
Stage 2 Approved Investment (2023)US$4.9 billion
Stage 2 Revised Investment (2026)US$6.9 billion
Construction Status16% complete
Expected First ProductionLate 2031
Stage 2 Production CapacityApproximately 4.36 Mtpa
Combined Jansen Capacity (Stages 1 and 2)Approximately 8.5 Mtpa
Stage 1 First ProductionMid-2027
Expected Share of Global Potash SupplyApproximately 10% from the whole project
Strategic PurposeBHP’s diversification into fertilizer minerals

Project Team
DeveloperBHP Group
Major Engineering and Construction Partners:
- Fluor Corporation – Engineering, procurement and construction management for Stage 2
- Aecon Group Inc. – Construction contractor for Stage 1 infrastructure works
- Wicehtowak Aecon LP – Indigenous partnership contractor supporting project delivery
Outlook on BHP’s Jansen Potash Project Development in Canada
Although the latest cost escalation and schedule revision present a setback for the development, BHP continues to view Jansen Potash project as a cornerstone asset capable of generating significant long-term value. The company believes growing global demand from the agriculture sector will support the project’s economics over its multi-decade operating life.
With Stage 1 progressing toward first production in 2027 and Stage 2 construction continuing, Jansen Potash project development remains one of the largest mining investments currently underway in North America alongside others such as Tahuehueto Gold-Silver Mine in Mexico. It is also one of the most significant new sources of potash supply expected to enter the global market during the next decade.