Gopher to Badger transmission line

Rural residents are fighting the $1.2 billion Gopher to Badger transmission line in southeast Minnesota. The citizens group NO765MN has stepped up town hall meetings along the way. In addition, the 765-kilovolt project is supported by Xcel Energy and Dairyland Power Cooperative. The Minnesota Public Utilities Commission has not yet given its approval to the line.

The project forms part of a wider grid push. In 2024, the Midwest Independent System Operator approved a $22 billion plan. It includes 24 projects in nine states, including Minnesota. In addition, the southeast Minnesota route, the MariBell Segment, is a line from South Dakota to Wisconsin.

Other Projects

On other energy projects, the Savannah River plutonium plant secured a $23.5 billion cost baseline and a December 2038 completion date. The US Department of Energy approved the baseline and gave full construction approval on Oct. 15. In addition, the National Nuclear Security Administration confirmed the $23.5-billion amount. Meanwhile, the project turns the unfinished shell of the abandoned MOX megaproject into a plutonium-pit production plant.

Scope of the Gopher to Badger transmission line

The 765-kilovolt line is one of the largest ever proposed in the United States. Furthermore, steel lattice structures 200 feet tall would carry the lines, about the size of a 15-story building. Towers would be built every 1/4 mile along the 140-mile route, almost three times the height of the existing 161-kilovolt towers in the area. Furthermore, the path passes by the villages of Caledonia, Harmony and Spring Grove. It therefore cuts through wooded bluffs and farmland in the karst-rich Driftless Area.

The utilities say the upgrade is long overdue. “If you can think of a highway system not being updated in 70, 75 years, that’s what we’re looking at, right?” said Katie Thomson, Dairyland’s spokesperson. In addition, she quoted demand growth of 25 percent or more over the next 20 years. Opponents, meanwhile, argue that the line does not provide power to homes along its route. NO765MN leader Kyle Johnson explained the acoustic effect at a Mazeppa town hall: “It will be a constant humming industrial noise that you can’t turn off, you can’t walk away from, and it will go right through people’s homes.

Concrete costs the human toll. Allie Kuppenbender and her husband Tony Lent are the owners of Bleed Heart Floral Farm and Design in Mazeppa. The path runs through their 14-acre land. In addition, their hoop houses are located within the proposed easement. Approval would cause the structures to collapse, along with tens of thousands of dollars of woody perennials. Xcel was willing to purchase the farm, Kuppenbender says. However, the offer is not as much as their investment. It’s devastating, this was our dream,” she said. Meanwhile, almost 600 comments have been submitted to the PUC. More than 60 residents attended the Nov. 16 Mazeppa meeting.

Outlook for the Minnesota transmission line fight

The alternatives dispute now becomes the basis for the review. NO765MN volunteers conducted research on undergrounding, route adjustments and direct-current conversion, claiming that these would save ratepayers money. But both utilities told MPR News they considered the options and determined they were impractical. In addition, they said, burial requires a lot of digging and has a high environmental footprint. The cost of converter stations would be hundreds of millions of dollars. Zumbro Falls resident Devon Ballinger already submitted a comment and will be submitting additional comments.

Finally, the timeline has been shifted to the state process. The PUC has yet to approve the project, public hearings await. Also, NO765MN is still soliciting comments before them. Furthermore, KTTC reported construction starting around 2030 and service following about two years later. The battle is now focused on the hearings, where the residents’ comments are the primary weapon. Consequently, the review window determines the route, the easements and the farms along the way.

Gopher to Badger transmission
Rural residents are fighting the $1.2 billion Gopher to Badger transmission line in southeast Minnesota.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *