Project Fact Sheet
NameSpherical Tokamak for Energy Production (STEP) Fusion Powerplant.
LocationWest Burton, Nottinghamshire, England, United Kingdom.
TypePrototype nuclear fusion power station.
Development StatusDesign development, procurement and pre-construction preparations.
Original Site SelectionOctober 2022.
Construction Start TargetAround 2030.
Target First Operations2040.
Initial Construction Contract£200 million.
Initial Contract DurationThree years.
Wider Construction OpportunitiesUp to £10 billion.
Additional Engineering ProcurementUp to £115 million.
Government Funding Allocation£1.3 billion towards STEP over four years.
Wider Government Fusion Commitment£2.5 billion over four years.
Target Net Electricity DemonstrationMore than 100MW.
Peak Construction WorkforceUp to 8,000 onsite jobs.
Tender Submission DeadlineJanuary 29, 2027.
Expected Contract AwardsApril 6, 2027.
Expected Engineering Contract CommencementApril 23, 2027.
Project Team
Developer and Delivery AuthorityUK Fusion Energy Ltd (UKFE).
Parent OrganizationUnited Kingdom Atomic Energy Authority (UKAEA).
Government SponsorDepartment for Energy Security and Net Zero.
Chief Executive OfficerPaul Methven, UK Industrial Fusion Solutions, at the March 2026 appointment announcement.
Construction PartnerILIOS Consortium.
Lead Construction Joint Venture PartnersKier and Nuvia.
Engineering and Infrastructure PartnerAECOM.
Architectural PartnerAL_A Architects.
Programme and Cost Management PartnerTurner & Townsend.
Fusion Technology and Research PartnerUK Atomic Energy Authority.
Magnets System PartnerTokamak Energy.
Construction Partner Programme DirectorSimon Matthews.