Poland’s First Nuclear Power Plant: Project factsheet
- Location: Lubiatowo-Kopalino, Choczewo municipality, Pomerania
- Developer: Polskie Elektrownie Jądrowe (PEJ)
- Technology provider: Westinghouse Electric Company
- Engineering and construction partner: Bechtel
- Reactor technology: Westinghouse AP1000
- Number of reactors: Three
- Combined generating capacity: Approximately 3,750 MW
- Estimated project investment: Approximately $50 billion
- Latest development: PEJ and the Westinghouse-Bechtel consortium signed a letter of intent on November 19, 2026, to advance additional long-lead equipment procurement
- Polish manufacturers receiving conditional purchase orders: Energomontaż-Północ Gdynia, FAMAK, Mostostal Kielce and Mostostal Kraków
- Other equipment procurement: IHI Corporation received an order for engineering and procurement activities for long-lead containment vessel and steel-module items
- EPC contract status: Main commercial terms agreed in September 2026; full contract signing expected by the end of the first quarter of 2027
- Site preparation: Grading, levelling, drainage, temporary roads and geological investigations
- Nuclear construction permit application: Submitted in March 2026
- Target for first nuclear concrete: Fourth quarter of 2028
- Target commercial operation: Unit 1 in 2036, Unit 2 in 2037 and Unit 3 in 2038
- Expected electricity contribution: Approximately 10% of Poland’s electricity demand