Talanta Rail Link Set for December Completion, Moving 1,500 Passengers Every 10 Minutes

Home » Transport » Rail » Talanta Rail Link Set for December Completion, Moving 1,500 Passengers Every 10 Minutes
Talanta Rail Link

Project Fact Sheet

Project NameNairobi Central–Kibera–Talanta Stadium Commuter Rail Link.

Project TypeCommuter railway rehabilitation and extension.

LocationNairobi, Kenya.

Length11.5 kilometres (latest government announcement; some media reports cite 13.3km).

Completion DeadlineDecember 15, 2026.

Implementing AgencyKenya Railways Corporation (KRC).

Main ContractorChina Road and Bridge Corporation (CRBC).

Passenger CapacityApproximately 1,500 per trip; planned high-frequency service at 10-minute intervals.

Train TypeEight-coach Diesel Multiple Unit (DMU).

Maximum SpeedUp to 60km/h.

Journey TimeApproximately 15 minutes between Nairobi CBD and Talanta station.

StationsNyayo Stadium, Mbagathi, Kibera and Talanta Sports City.

Project CostNot publicly disclosed separately.

Construction StartSeptember 2026.

Key WorksTrack rehabilitation, concrete sleeper replacement, drainage, new rail spur, stations and pedestrian safety infrastructure.

Project PurposeStadium access, commuter mobility, congestion reduction and railway network modernisation.

Project Team

Developer and Implementing AgencyKenya Railways Corporation.

Government OversightState Department for Transport, Ministry of Roads and Transport.

Principal SecretaryMohamed Daghar.

Kenya Railways Managing DirectorPhilip J. Mainga.

Main ContractorChina Road and Bridge Corporation (CRBC).

CRBC Kenya General ManagerSheldon Yu Xiaodong.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.