TEPCO Reviews Kashiwazaki-Kariwa Nuclear Facility Schedule After Construction Problems

Home » Energy » Nuclear » TEPCO Reviews Kashiwazaki-Kariwa Nuclear Facility Schedule After Construction Problems
TEPCO reviews construction schedules at Kashiwazaki-Kariwa Nuclear Power Station after concrete issues and contractor delays.

Project team

The wider construction history of the Kashiwazaki-Kariwa Nuclear Power Station includes major Japanese engineering and construction companies such as Kajima Corporation, Hazama Ando Corporation, Shimizu Corporation, Takenaka Corporation and Maeda Corporation. Nuclear industry suppliers Toshiba, Hitachi and General Electric have also been associated with the station’s development. TEPCO remains the plant operator and is overseeing the current construction schedule review for the Specific Major Accident Response Facilities at Units 6 and 7. However, the companies listed above should be regarded as historical project participants, not confirmed contractors for the current safety-facility works.

TEPCO reviews construction schedules for Kashiwazaki-Kariwa nuclear safety facilities after concrete issues and contractor delays.
TEPCO reviews construction schedules for Kashiwazaki-Kariwa nuclear safety facilities after concrete issues and contractor delays.

Kashiwazaki-Kariwa Nuclear Power Station: Project factsheet

  • Project: Kashiwazaki-Kariwa Nuclear Power Station – Specific Major Accident Response Facilities
  • Country: Japan
  • Location: Kashiwazaki and Kariwa, Niigata Prefecture
  • Operator: Tokyo Electric Power Company (TEPCO)
  • Affected units: Units 6 and 7
  • Construction scope: Specific Major Accident Response Facilities for the two reactors
  • Purpose: Additional protection against severe accidents, including deliberate aircraft impacts
  • Previous Unit 7 facility completion target: August 2029
  • Previous Unit 6 facility completion target: September 2031
  • Reported Unit 7 completion aim: April 2031, as reported by Bloomberg; not a formally confirmed revised schedule
  • Latest development: TEPCO announced on November 26, 2026, that it would review the construction schedule after construction issues and a contractor request to revise the work programme
  • Current schedule status: Revised completion dates have not been determined
  • Unit 7 status: Not yet returned to operation

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *