Project Factsheet
Parent ProgramU.S. Army Strategic Capital Initiative (SCI), launched February 27, 2026, to leverage private capital and industry expertise for military modernization.
Strategic PillarEnergy Resilience and Dominance (Pillar 1 of 6).
ObjectiveLease underutilized, non-excess Department of the Army (DA) land to private, public, or non-profit developers to build commercial power generation facilities alongside optional data centers, maximizing financial returns for the Army while securing independent base power.
Selected Locations (9 Installations)
- Joint Base Lewis-McChord, Washington
- Fort Bragg, North Carolina
- Fort Hood, Texas
- Fort McCoy, Wisconsin
- Fort Rucker, Alabama
- Blue Grass Army Depot, Kentucky
- Pine Bluff Arsenal, Arkansas
- Tooele Army Depot, Utah
- Sierra Army Depot, California
Core Requirements & Guidelines
- Power First: Stand-alone power generation proposals are permitted, while data-center-only proposals are automatically disqualified. Approved power sources include nuclear reactors, natural gas, battery storage, and other commercial technologies.
- Grid Outage Resilience: Facilities must supply backup electricity to their host bases within 1 hour of a grid failure and sustain power for at least 14 continuous days.
- Strict Water Rules: Data center cooling must be water net-neutral or better. Developers cannot draw from freshwater aquifers and must fund and source alternative non-potable water—such as industrial greywater, treated municipal effluent, brackish groundwater, or closed-loop cooling systems.
Key Timeline
- Feb. 27, 2026: Strategic Capital Initiative officially launched.
- Nov. 30 – Dec. 17, 2026: On-site installation tours for prospective developers.
- Jan. 18, 2027: Final deadline for project proposals.
Project Team
- Lead Agency: Department of the Army (Office of the Assistant Secretary of the Army for Installations, Energy and Environment / Strategic Capital Initiative Office).




Leave a Reply