Yokeshire Water's wastewater treatment plant

Factsheet: Yorkshire Water AMP8 Overhaul

  • Project Name: AMP8 Environmental Investment Programme
  • Total Budget: £8.3 Billion (2025–2030)
  • Current Capital Spend: £1.1 Billion (April 2026 – April 2027)
  • Key Civil Contractors: Kier, Galliford Try, and Arup
  • Primary Objective: Modernise Victorian infrastructure to eliminate river pollution and reduce network leaks.

Budget Allocations

  • Storm Overflow Schemes: £1.5 Billion
  • Complex Engineering Works: £850 Million
  • Clean Water Main Replacements: £406 Million
  • Artificial Intelligence & Tech: £32 Million

Major Project Milestones

  • March 2026: EQT acquires a 42% stake in Kelda Holdings to inject fresh funding into the project.
  • June 2026: Yorkshire Water awards a massive £80m technical design framework to 15 firms (including a £50m partnership with Arup).
  • June 2026: Launch of the 5-year AI framework with Jacobs and deployment of 1,500 Samotics smart-monitoring sensors.
  • Autumn 2026: Scheduled completion of the flagship drought-resilience water main in Bradford.
  • 2030 Goal: Full upgrade of 450 targeted storm overflows and 1,085 kilometres of replaced water mains.

Also readSouthern Water latest £540m contract for 5-year spending period

Also readStrabag-Equitix JV selected for UK’s £2.9bn Haweswater Aqueduct project

Project Team

Client / Framework ownerYorkshire Water

FrameworkAMP8 Complex Non-Infrastructure Works Framework (2025–2030), valued at £850 million, with an optional five-year AMP9 extension

Appointed contractor partners:

  • Barhale — appointed to Lot 1 (complex works); civil, mechanical and electrical delivery
  • Galliford Try (Environment business) — civil engineering and full-phase delivery; appointment expected to be worth around £100 million to the firm
  • Glanua — process, mechanical and electrical works
  • Kier (Water business unit) — non-infrastructure clean and wastewater works
  • Mott MacDonald Bentley (MMB) — complex design-and-build works across the framework
  • Tilbury Douglas — building, civil and MEICA capability
  • Ward & Burke — civil engineering and design-and-build delivery

Scope of worksCivil engineering; mechanical, electrical, instrumentation, control and automation (MEICA); and building works across Yorkshire Water’s clean water and wastewater (non-infrastructure) assets

Wider programmePart of Yorkshire Water’s £8.3 billion AMP8 investment programme (2025–2030), approved by regulator Ofwat

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *